Location: Banke
District of the Mid Western Development Region, Nepal
Owner: Ministry of
Water Resources Department of Irrigation, Government of Nepal
Work Duration:
2006-2010
Financier:
Government of Nepal
Feature: Provide
year-round irrigation to a cultivable command area of 33,766 ha on the right
bank of the Rapti River
Project Proposal for the Implementation of Sikta Irrigation
Project
Background
The Sikta Irrigation Project is situated in the Banke District
of the Mid Western Development Region. The Project, with a cultivable command
area 33,766 ha including the rehabilitation of Dunduwa Irrigation system,
constructed by Indian Cooperation Mission in 1964, would irrigate almost all
the low lands of the
Banke District and its economic impact could be significant for this development region. The Project area comprises 34 Village Development Committees (VDCs) and the municipality of Nepalgunj, which is the District head quarter. The irrigated area can be further extended by 9,000 ha of 9 VDCs lying on the left bank of Rapti River.
Banke District and its economic impact could be significant for this development region. The Project area comprises 34 Village Development Committees (VDCs) and the municipality of Nepalgunj, which is the District head quarter. The irrigated area can be further extended by 9,000 ha of 9 VDCs lying on the left bank of Rapti River.
The concept for the Sikta Irrigation Project was first
formulated in pre-feasibility studies conducted from 1975 to 1976 and contained
in the report on the proposed Western Rapti Multipurpose Development, which
comprised the construction of a high dam at Bhalubang of Dang District with a
storage reservoir for irrigation and hydropower development in the West Rapti
Basin and adjacent areas such as Kapilvastu.
The German company Lahmeyer International GmbH completed a
feasibility study for Sikta Irrigation Project in August 1980 based on a
run-of-the-river diversion gravity irrigation scheme. A further study for a
run-of-the-river scheme was carried out by the then Department of Irrigation,
Hydrology and Meteorology and this was completed in June 1983. However, due to
unavailability of external funding, the project could not be developed until
2002, when Irrigation Development Project - MWR decided to reassess the
project. In April 2004, the feasibility study report was submitted by the
IDP-MWR after having a rigorous field level study. The study showed that the
project is technically, economically and socially viable in the present context
as well. Based on the Feasibility Study Report 2004, the Government of Nepal
decided to implement the Project in three phases, which are as follows. The
total cost of the Project as per the Study is NRs 7.45 billion (revised to NRs
12.80 billion in Fiscal Year 2007/08).
Phase I - Construction of Headworks and Desilting Basin
Phase II - Construction of Main Canal and Branch Canals
Phase II - Command Area Development
In view of the relatively high incidence of rural poverty in
Banke District in the Mid Western Development Region - 40 percent of the rural
households fall below the poverty line -, the small number of existing
irrigation facilities and the limited local surface and groundwater resources
in the district which would be suitable for small or medium scale irrigation
development, Government of Nepal (GON) has therefore given a high priority to
the implementation of the large scale Sikta Irrigation Project which would
irrigate about 43,000 ha of land (including the proposed extension on the left
bank) in the District. The water source for this project is the West Rapti
River, which originates from the mid-mountains in the Mid Western Region of the
country, having average annual flow of about 120 m3/s.
The overall goal of the Sikta project is to contribute to
the National Development Objectives of GON and to improve the standard of
living of the people in Banke District. This would be achieved by the provision
of irrigation facilities together with the improvement of agricultural support
services, which would improve the agricultural productivity so that
agricultural production and thus incomes of the rural population would be
increased.
Project Area
The Project Area is located in the Banke district of the Mid
Western Development Region of Nepal. It covers 34 Village Development Committes
and one Municipality of the District. Nepalgunj is the headquarter of Banke
district and although the administrative head quarter of the Mid Western
Development Region is Birendra Nagar in the Surkhet District, Nepalgunj remains
the commercial centre of this Region. The Project area is enclosed by the
East-West Highway (Mahendra Rajmarg) to the North, the national boundary to the
South, Dang District in East and Mankhola to the West. Geographically the area
comprises lands between 280 00\\\\\\\\\\\\\\\' and 810 14\\\\\\\\\\\\\\\' N
latitudes and 810 32\\\\\\\\\\\\\\\' and 810 57\\\\\\\\\\\\\\\' E longitudes A
location map of the project area is shown in Figure 1.
The headworks under construction lies within 300 m of the
highway at the Agaiya village about 58 km east of Nepalgunj. The project area
is accessible by the national highway (Mahendra Rajmarg) by road. The district
headquarters of Nepalgunj is connected from Kohalpur with the national highway
by a regional highway which continues up to the Nepal-Indian Border crossing at
Rupaidhiya.
Nepalgunj has all weather airport having daily flights from
Kathmandu. This airport is a hub for most of the air service to the remote hill
districts in the Mid Western Development Region.
\"\\"\\\\"\\\\\\\\"\\\\\\\\"\\\\"\\"\"
Water Resources
Of all the streams and rivers in the District, the West
Rapti river, although rain-fed, is the only river with a significant perennial
flow during the dry season and is therefore proposed as source for the
irrigation system. The drainage area of the Rapti River lies in the Mid Western
Region of Nepal between elevations of 140 to 4000 m asl. The total length of
the river to the proposed diversion site as about 280 km, and the catchment
area covers 5,459 km2 at this diversion site. The Rapti river is formed by the
confluence of two main rivers in the Mid-Western hill region, the Madi khola
and the Jimruk khola, the more important being the Madi Khola which has two
tributaries; the Lungri and Arung kholas.
The Rapti river has been gauged since 1964. The nearest
gauging station to the proposed diversion site is at Jalkundi about 42 km
upstream from the site with the catchment area of 5,150 km2. This station has
hydrological records since 1964. In the absence of long term gauging at the
intake site selected for the Project, the hydrological analysis is based on the
records of Jalkundi.
The mean monthly discharge, median monthly discharge and 80
% reliable flow for Rapti River at Jalkundi is presented in Table 3-3.
Table 3 1: Monthly Discharge of West Rapti River at Jalkundi
Discharge in m 3/s
Month Jan Feb. March
April May
June July Aug. Sept Oct
Nov Dec
Mean monthly discharge 32.4
27.4 22.4 17.6 19.5 112
333 451 370 149 61.7
39.8
Median monthly discharge 28.1
24.8 19.8 14.4 10.8 64.7
251 380 291 120 52
34.1
80 % Reliable discharge 24.8
20.8 16.7 12.5 8.56 50.4
212 348 233 94.4 42.8
30.7
The Irrigation Infrastructure
To provide irrigation water to 33,766 ha of Banke District,
the Project would construct a run-of-the-river, gravity irrigation system,
which would comprise the following principal works.
A barrage with a
total length of 317 m across the Rapti adjacent to the Agaiya village on the
East West Highway, backing up the river flow to a sufficient elevation to
command 33,766 ha.
An intake head
regulator is designed for a maximum diversion capacity of 62.5 cumecs, 50
cumecs for the right bank main feeder canal and 12.5 cumecs for flushing from
the settling basin. The canal intake structure with two gated openings and a
two chamber desilting basin.
A canal head
regulator on the left side will be provided for the diversion of water to
irrigate 1,800 ha, the command area of Rajkulo Irrigation Project.
A lined feeder
canal section of the main canal with a maximum discharge capacity of 50 cumecs,
about 50 km parallel to East-West Highway to serve the main cultivable command
area 33,766 ha on the right bank of the Rapti. The canal will have a total of
91 structures out of which 66 are minor and 25 are major. The structures
comprise of siphons, aqueducts, highway crossings, village road bridges and
covered canals. The canal will be flanked along its length by an all-weather
inspection road. The feeder canal will enter the command area about 2 km. south
of Kohalpur.
A main canal (50
km) and secondary, sub-secondary canals (233 km) delivering water to 85 ha
blocks in the command area, flanked by all weather inspection roads and
provided with appropriate control, measurement and auxiliary features.
An open drainage
system will be developed starting from the field channel to collector drain and
subsequently connected to tertiary, secondary and primary drains. No salinity
symptoms in land irrigated from tube wells or from existing surface lifting
systems are observed.
River bank
protection works will be provided to control the erosion along the Rapti and
Dunduwa rivers.
The Project would incorporate the existing ground water
irrigation facilities and the two existing surface lift irrigation systems in
the water distribution system to allow a structures conjunctive use of the
irrigation facilities. Since the discharge in the Rapti River would only allow
to start diversion for the monsoon crop in the main command area in the middle
of June , therefore the existing groundwater facilities would be very important
for the establishment of nurseries for paddy cultivation.
The above infrastructure development works do not include
the infrastructures to be developed on the left bank for 9,000 ha. The works on
the left side will be planned after conducting a feasibility level study, which
will be carried out in the F/Y 2008/2009.
Development Plan
The Project would construct a run-of-the-river, gravity
irrigation system, which would comprise the following principal works to be
implemented in three phases.
The Figure 2 shows the Project Development Plan, which has
been divided in the three Phases and various steps within the phases. As shown
in Figure 3, the project will be implemented in three Phases as given below.
Phase 1 - Construction of Headworks
Phase 2 - Construction of Main Canal and Branch Canals
Phase 3 - Command Area Development Works
Phasewise breakdown of the works in each of the Phases is
given below.
Phase I : Step
1: Civil Works for Headworks Construction
Step 2: Electromechanical part of Headworks
Phase II : Part
1: Main canal from Ch 0+614 to Ch 15+000
Part 2:
Step 1: Main canal from Ch 15+000 to 35+000 Km.
Step 2: Branch (Secondary) Canals
Sidaniya Branch
(16 km)
Offtaking point:
Ch 28+000 Km of Main canal
Command area:
1,711 ha.
Dunduwa Branch
19.00 Km
Offtaking point:
Ch 32+900 Km of Main canal
Command area : 16,780
ha.
Akalgharwa Branch
(5.30 km)
Offtaking point:
Ch 34+800 Km of Main canal
Command area : 905
ha.
Step 3: Sub secondaries and tertiaries of above Branch
canals.
Part 3:
Step 1: Main canal Chainage 35+000 to Ch 50+000 Km. (upto
Manpur river)
Step 2: Branch (Secondary) Canals
Gohawa Branch
(3.00 km)
Offtaking point:
Ch 36+400 Km of Main canal
Command area : 229
ha.
Parsenipur Branch
(11.00 km)
Offtaking point:
Ch 37+300 Km of Main canal
Command area :
1,328 ha.
Pirari Branch (3.50 km)
Offtaking point:
Ch 38+900 Km of Main canal
Command area :
1,310 ha.
Guruwagau Branch
(18.00 km)
Offtaking point:
Ch 40+700 Km of Main canal
Command area :
8,129 ha.
Step 3: Sub-secondary and tertiary of above Branch Canals
Phase III : Command
Area Development works
Present Status Of The Project
Institutional Set Up
The Department of Irrigation under the Ministry of Water
Resources is the responsible organization to implement the Project. The DOI has
already established a Project Office, namely Sikta Irrigation Project (SIP), at
Nepalgunj, the district headquarters and deputed nine professional staff and
adequate number of supporting staff for the execution of the Project. The SIP
has already started the implementation of Phase 1 works.
Phase 1 Works
The SIP has contracted out the Construction of Headworks to
SINOHYDRO-LUMBINI Joint Venture in June 5, 2006 through an International
Competitive Bidding. The contract amount is NRs 1.85 Billion. The works
included in the contracts are given below.
Construction of
317 m long diversion structure across Rapti River at Agaiya, Banke
Construction of
head regulators on the both sides of the river
Construction of
desilting basin of 650 m length on the right bank (62.5 m3/s capacity)
Construction of
guide bank (about 700 m)
The Construction of headworks has already been started from
Novermber 1, 2006. It has been planned to complete nearly one third of the
headworks construction within the current Fiscal Year 2063/64 (July 15, 2007).
The total construction period for the construction works under the contract is
42 months, which ends in December 31, 2009.
Phase 2 Works
For the construction of Main Canal from Chaiange 0+614 to
12+036, selection of the Contractor is in process and the Contract will be
awarded within January 2009. Three contracts have been awarded to the local
contractor for the construction of the Main Canal from Chainage 12+036 to
15+000 km.
No comments:
Post a Comment